CCCC Shanghai Dredging Co., Ltd. won the bid for West Yalu River Channel Regulation project

CCCC Shanghai Dredging Co., Ltd. won the bid for West Yalu River Channel Regulation project

Write: Neeraj [2011-05-20]
Recently, CCCC Shanghai Dredging Co., Ltd. won the bid for dredging project of channel regulation of Yalu River. The contract value amounts to RMB 104.77 million, with construction period of 455 days.
The project is located in Dandong border economic cooperation zone, with total dredging volume of approximately 8,850,000m3. It has been started working at 15 August 2008 and will be finished on 16 November 2009.