Elastic layer of acrylic stadium construction plan
Write:
Olga [2011-05-20]
Description:
Elastic layer of acrylic stadium construction plan
(In accordance with standards of the International Tennis Federation ITF)
1, Water: Grand sprinkler test site preparation, testing the ground water after an hour more than 3mm Department depression and mark with chalk.
2, complement level: the imported asphalt tennis courts dedicated a filler level up to 5 # 5 # 40-70 head-doped quartz sand, cement and water, filling the venue depression, reduce water phenomenon, so the ground up to standard pitch requirements: a ruler measure the height difference does not exceed the ground within 3m 3mm. Dry about 24 hours.
3, bottom: with a special asphalt filler imported tennis Grand Scraping 5 # 5 #-doped layer to 40-70 head quartz sand, cement and water, mix thoroughly after scraping with a rubber rake Scratch imported to form a layer can closely adhere to the original surface coating on the golf course, 100% for the water-based acrylic coating to provide high-quality floor. Dry about 24 hours.
4, elastic layer: the audience particles coated with acrylic scratch layer (2 thick 1 thin) layer of coarse particles: coarse particles with acrylic 100A # Scratch the second floor; 100A # is a thick, flexible and 100% acrylic latex. Mixed selection of large pieces of special high elastic rubber. Scratch diluted with water, to provide appropriate flexibility for the court to make playing more comfortable. Layer of fine particles: small particles with acrylic 100B # Scratch layer; 100B # 100A # acrylic coarse particles for the layer. For leveling coarse particles form a layer of large particles pieces of rough surfaces. Use 100B # It will provide high-quality smooth elastic layer. After the acrylic paint is conducive to the construction.
5, the enhancement layer: acrylic filler audience Scraping 4 # 4 # acrylic filler layer to dilute water mixed with 60-80 mesh quartz sand. After fully mixing the imported rubber scraper rake Scratch. Provided at the bottom of a layer on top of thick cushion to increase the pitch strength, improve the quality of the entire court surface. Dry about 24 hours.
6, the texture layer: acrylic pigment (plus quartz sand) Overall Scraping acrylic pigment layer to dilute water plus 80-100 mesh silica sand, mix thoroughly after scraping with a rubber rake Scratch imports. To have uniform surface texture effects, increasing wear-resistant function and regulation ball. Each layer dry and conservation needs for 24 hours.
7, finishing layer: Scraping the audience with a layer of acrylic pigment to dilute water diluted acrylic pigments, without the import of sand to mix with the rubber scraper after the rake Scraping. So colorful and pleasing to the eye surface, and the climate and ultraviolet radiation has a strong resistance, more beautiful and durable surface course. Conservation of dry and about 24 hours. Texture layer plus three finishing layer of pigment
8, line: line of paint with white acrylic paint standard 9 # 1 tennis court boundary line set by international standards, measurements, affixed with adhesive tape machine will be imported by line tight sticky tape on the ground to prevent the edges, brush with a brush directly Acrylic paint coating a layer of white lines.
Description:
asphalt should be based on more than 95% density, flatness measuring 3 meters ruler, depression, no more than 3mm. The basis of an unsatisfactory or if the asphalt surface is too rough, asphalt base material will increase the amount of # 5.
construction of the temperature should be above 12 , easy-curing coatings, and more than 36 paint is bubbling. Construction requirements and the ground drying paint (each layer must dry before they can continue to Scratch), can guarantee the best quality construction.
After completion of course, the best re-use conservation of more than three days.
paint 55 gallons / bucket, 5 gallon / pail, 1 gallon of marking paint / small tin.
does not support the original concrete base outside the elastic layer of acrylic tennis court as a basis, it is recommended to use more of the asphalt concrete foundation.
Specifications:
3mm thickness can be adjusted according to customer needs