Cadres Conference required This Year s

Cadres Conference required This Year s

Write: Cleopatra [2011-05-20]

On November 2, 2009, CFHI held a cadre conference for recognizing the current situation and the target, building up the firm confidence and clarifying the key points of working. The board chairman of CFHI, Mr. Wu Shengfu, required all the cadres and the staff members should be confident, overcome difficulties, make great efforts above average and take every possible measure to accomplish this year s production value target of 12billion yuan as well as be prepared for next year s work.

The masses of the staff members, especially the cadres must push CFHI into a new developing stage with the spiritual outlook of fearing no hardship and striving for success. Mr. Zhao Lixin, CFHI s Party Committee Secretary, presided over the conference and he put forward four requests for fulfilling the meeting s spirits.

The participants are as follows, Li Ziling, Ma Ke, Cai Lianzhong, Zhang Zhenrong, Liu Dengyun, Sun Min, Fu Qun, Zhu Qingshan, Liu Changren and the assistant of CFHI President as well as people in charge of Party and Policy affairs from different departments.

At first, Mr. Wu Shengfu summed up CFHI s main job within the first 10 months this year. He pointed out that with the hard working of the whole staff members and cadres, CFHI has accomplished the production value of 9.23 billion yuan which is 77% of the planned annual amount, the production yield of 162.

6 thousand tons which is 81.3% of the planned annual yield, the molten steel 252.28 thousand tons which is 74% of the planned annual yield, the forgings and castings output of 119.7 and 24.3 thousand tons respectively, which are 74.58% and 76% of the planned annual yield accordingly. In the business filed, the first three quarters realized 5.

77 billion yuan of products sales. In scientific research, nuclear castings and forgings have made a big progress, the delivery of all the 3-generation AP1000 type of reactor nuclear forgings have already been finished except some individual parts. CPR1000 reactor also has made great progress. In technical improvement, the financing for the international first-class casting and forging steel base in Fularji and Dalian nuclear island one-loop construction project has already finished and these projects have been going on in proper sequence.

The casting and forging steel base entered its last stage; however, some of the projects are developing not so rapid. With the great efforts by all sides of CFHI and relevant departments, the progress of going into public is generally satisfying. Some certain of achievements have been made in products quality and safety environmental protection fields but there are still some deficiencies to be solved with efforts.

At last, Wu Shengfu hopes all the people of CFHI can realize the current development situations that is as sailing against the current, either go ahead or keep falling, people can hold together and not only with pains but also with skills to enhance the innovation ability and finish this year s production and business task, to maintain the good growth momentum and not make the nation and the families of all the staff members disappointed in order to create a splendid tomorrow for CFHI s development with diligence and fighting and enterprising spirits.

The Secretary Zhao Lixin put forward specific requirements about how to apply the meeting s spirits.