Home Facts company

The First Pile of Pelabuhan Ratu Project in Indonesia Fell Down

The First Pile of Pelabuhan Ratu Project in Indonesia Fell Down

Write: Tulip [2011-05-20]

The First Pile of Pelabuhan Ratu Project in Indonesia Fell Down

The first pile of Pelabuhan Ratu project in Indonesia, generally contracted by Shanghai Electric PG gorup, 3 350MW units, fell down on the day of Mar. 1st. This action means that the ground construction of the project has generally started.

It is recorded that the contract is the largest in Indonesia s single contract history till now, it is also the first EPC project through which Shanghai Electric entered into the Indonesia market.

Publishing Date: 2008-03-27 Hits 28