From Oct. 15 to 16, two wind power projects (Yangshugou, Dishuihu) of Longyuan (Hebei Weichang) Company and Phase 2 of Guazhou 300MW self-reliance large-sized demonstration project of Longyuan (Gansu) Company affiliated to China Longyuan Power Group Corporation Limited were put to operation one by one. The installed capacities of the above three projects are 49.5MW respectively.
The two projects are located in Weichang County, Hebei Province, whose construction were started on May 1, 2010 and were completely put into production on Oct.15, 2010.The two projects are the fifth and the sixth projects following the four projects including Zhangjiawan, Shanwanzi, Guangfayong and Zhuzixia constructed by Longyuan(Hebei Weichang) Company, whose accumulated installed capacity is 297MW.
After 5 months unremitting efforts, the entire staff of Longyuan(Hebei Weichang) Company overcame the poor weather conditions, the difficulty of transporting equipments and the lack of staff in Bashang area of Weichang County. Finally, Dishuihu and Yangshugou Projects were put into operation smoothly.